BGE Russett to Tipton

Download Complete Project Profile

Location:

Fort Meade, MD

Project Details:

Aaron Enterprises, Inc. was contracted to install 23,000 LF of 30” diameter HDPE conduit bundles for 230kV electric lines by HDD. The crossings were installed as three separate parallel installations ranging from 1,100 LF to 2,600 LF. Several environmentally sensitive features with a fixed inadvertent return (IR’s) disturbance area were crossed. AEI employed a comprehensive instrumentation program that successfully reduced the risk and impact of IR’s while drilling. See attached paper presented at the ASCE Pipelines 2017 Conference below for more details.

Final Product:

(5) 10”, (1) 4” HDPE Bundle

Geology:

Hard sticky clay, 50 plus blow counts

Category: Horizontal Directional Drilling Projects, Project ProfilesTag: Electric Projects

Innovation. Teamwork. Technology.

“Whatever It Takes” Since 1976

Contact us
  • Services
  • Markets Served
  • Projects
  • Employment
  • Who We Are
  • Contact
  • Link to Aaron Enterprises, Inc. YouTube page
  • Link to Aaron Enterprises, Inc. LinkedIn page
  • Link to Aaron Enterprises, Inc. Facebook page

(717) 854-2641


Gold Shovel Standard logo

Copyright © 2009–2023 · Aaron Enterprises, Inc. · All Rights Reserved · Powered by BizBudding Inc.