Location
Pittsburgh, PA
Project Details
Furnishing and installation of 235 LF of 48” diameter steel casing by trenchless methods. The crossing included soil stabilization along the bore path. AEI excavated a pit behind a slab on grade warehouse located adjacent to the main freight rails running along the Allegheny River into Pittsburgh. The crew installed a series of horizontal grout pipes and pumped a soil stabilizing grout to solidify the surrounding earth. A 48″ hydraulic steer head was used to auger bore the casing into place. The storm water crossing ended along the embankment of the Allegheny River where a barge was used to remove the head and complete the outfall structure.
Final Product
Installed 235 LF of 48” steel casing via Auger Bore
Geology
Gravels
Completion Date
February 2022
Installation Methods
- Auger Boring
- Guided Bore
- Soil Stabilization